7.答案如表所示:
时间 |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
10 |
11 |
12 |
13 |
MAE |
|
实际销售量 |
96 |
106 |
100 |
100 |
100 |
98 |
99 |
94 |
106 |
105 |
102 |
99 |
|
||
α =0.2 |
预测值 |
100 |
99.2 |
100.56 |
100.45 |
100.36 |
100.29 |
99.83 |
99.66 |
98.53 |
100.02 |
101.02 |
101.22 |
100.78 |
2.88 |
误差 |
-4 |
6.8 |
-0.56 |
-0.45 |
-0.36 |
-2.29 |
-0.83 |
-5.66 |
7.47 |
4.98 |
0.98 |
-2.22 |
|
||
α =0.3 |
预测值 |
100 |
98.8 |
99.02 |
99.31 |
99.52 |
99.66 |
99.16 |
99.11 |
97.58 |
100.11 |
101.58 |
101.71 |
100.9 |
3.06 |
误差 |
-4 |
7.2 |
0.98 |
0.69 |
0.48 |
-1.66 |
-0.16 |
-5.11 |
8.42 |
4.89 |
0.42 |
-2.71 |
|
8.解:
按第一种方案的计算结果如下(月产出按1800÷6=300确定):
月份 |
期初库存 |
实际产量 |
需求预测 |
期末库存 |
缺货数 |
缺货费用 |
超储 |
库存费用 |
正常时间总费用 |
1 |
0 |
300 |
200 |
100 |
0 |
0 |
100 |
100 |
600 |
2 |
100 |
300 |
200 |
200 |
0 |
0 |
200 |
200 |
600 |
3 |
200 |
300 |
300 |
200 |
0 |
0 |
200 |
200 |
600 |
4 |
200 |
300 |
400 |
100 |
0 |
0 |
100 |
100 |
600 |
5 |
100 |
300 |
500 |
-100 |
100 |
500 |
0 |
0 |
600 |
6 |
-100 |
300 |
200 |
0 |
0 |
0 |
0 |
0 |
600 |
合计 |
|
|
|
|
|
500 |
|
600 |
3600 |
总费用为:500+600+3600=4700
按第二种方案的计算结果如下【正常产出280;由于有最大加班量限制,当缺货量超过最大加班量时采用转包合同单位总成本小于自行生产(缺货+正常时间>转包合同),故在此时采用外包合同完成剩余产品生产】:
月份 |
期初库存 |
实际产量 |
需求预测 |
盈余表 |
加班产量 |
加班费用 |
外包数量 |
外包费用 |
超储 |
库存费用 |
正常时间总费用 |
1 |
0 |
280 |
200 |
80 |
0 |
0 |
0 |
0 |
80 |
80 |
560 |
2 |
80 |
280 |
200 |
160 |
0 |
0 |
0 |
0 |
160 |
160 |
560 |
3 |
160 |
280 |
300 |
140 |
0 |
0 |
0 |
0 |
140 |
140 |
560 |
4 |
140 |
280 |
400 |
20 |
0 |
0 |
0 |
0 |
20 |
20 |
560 |
5 |
20 |
280 |
500 |
-200 |
40 |
120 |
160 |
960 |
0 |
0 |
560 |
6 |
0 |
280 |
200 |
80 |
0 |
0 |
0 |
0 |
80 |
80 |
560 |
合计 |
|
|
|
|
|
120 |
|
960 |
|
480 |
3360 |
总费用为:120+960+480+3360=4920
由于第一种方案总成本低于第二种方案,故选取第一个总计划。